Large IT projects run 45% over budget on average, according to research by McKinsey and the University of Oxford that covered more than 5,400 projects. They also finish 7% late and deliver 56% less value than their business cases promised, which is the figure finance teams tend to forget. ERP sits squarely in that category. In November 2025, Gartner’s senior director of ERP strategy told the firm’s Barcelona symposium that 70% of ERP initiatives fail to fully meet their original business goals, and a quarter fail catastrophically. The overruns are rarely about the software itself, and fixing the decisions that cause them is a core reason Crunch-IS is a leader in ERP development services. Most of those decisions are made in the first three months. What follows is where the money goes, and what the projects that stay on budget do instead.

it

Time is the multiplier

The McKinsey and Oxford data found that cost overruns grew by 15% for every additional year a project was scheduled to run. Each month added to a plan is another month of consultants, backfilled staff, and two systems running side by side. The same research found that 17% of projects went so badly they threatened the survival of the company.

Birmingham City Council is the cautionary case everyone in the public sector now knows. Its Oracle program started with an estimate of £19 million plus a £1 million contingency, and finance was meant to go live in December 2020. In January 2026, the council’s forecast stood at £144.4 million through the 2027/28 financial year, and it was reimplementing the system from scratch. A long project is a risky project, whatever the plan says.

Four places the budget leaks

Gartner’s list of causes is blunt: bad business cases, unrealistic scope, underestimated complexity, and scope creep. In practice the money leaves through a few predictable doors.

  • Scope that keeps growing after sign-off. Every department that missed the requirements workshops arrives later with a “small” request. Twenty small requests make a second project.
  • Data migration treated as a weekend job. Bloor Research found that more than 60% of data migration projects overrun on time, budget, or both. Customer records with three addresses and supplier codes that changed in 2014 do not clean themselves, and they surface during testing, when every fix is expensive.
  • A go-live with no fallback. Revlon switched on a new SAP system in the US in February 2018, and its manufacturing plant in Oxford, North Carolina, could not ship to several large retailers. Its filings, as reported by Computer Weekly, put the damage at about $64 million in net sales it could not fulfill and $53.6 million in extra charges. Investors filed class action suits.
  • People work budgeted as a training line. Half of the organizations in a Panorama Consulting survey said the people and process side of ERP was as hard as the technical work, or harder. It rarely gets half the budget.

What the on-budget projects have in common

They do exist. Panorama surveyed 140 organizations that went live with ERP in 2021 and found that nearly 60% finished on budget, with only 10% significantly over. The ones that hold the line tend to share a handful of habits.

They freeze scope in writing and fund a separate, small change budget, so new requests compete for a fixed pot instead of quietly expanding the project. A request that cannot justify its share of that pot waits for phase two.

They move data early. Test migrations start in the first quarter of the project, against real records, so the ugly cases appear while there is time to fix them.

They phase the go-live. One plant, one region, or one business unit goes first, with a rollback plan that someone has actually rehearsed. Revlon’s real exposure was a single site carrying the whole risk with no way back.

They put a named business owner on every process, not just an IT lead on the project. When the warehouse manager owns the picking workflow, disputes about how it should work get settled in a day, not escalated for a month.

They also tie payments to working software. An integrator paid on the delivery of design documents is rewarded for producing documents. One paid when a user-acceptance test passes is rewarded for a system that runs the business.

project plan

Contingency is a forecast, not a buffer

A 10% contingency on a project whose reference class runs 45% over is a wish. Oxford’s research group has long argued for reference-class forecasting: start from what similar projects actually cost, then adjust for what is genuinely different about yours. Most ERP budgets do the opposite. They start from the vendor’s estimate and add a margin that feels prudent in the steering committee and looks naive eighteen months later.

The overrun is decided before the build starts

By the time a project is visibly over budget, the cause is usually a year old. It was an unclear business case, a scope nobody tested against the calendar, or a data set nobody opened. The projects that finish on budget are not luckier or simpler. They paid for those uncomfortable conversations in month one, when they were cheap, instead of in month eighteen, when every one of them comes with a consultant’s day rate attached.